Project timeline
1
Scoping Start
05/30/2013
2
Comment Period
05/30/2013
3
Decision
07/2013 (Estimated)
4
Implementation
10/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Facility Improvements/Construction |
| Crested Butte Mountain Resort Yurt Construction | Decision Signed Date: 07/30/2013 Legal Notice Date: 07/30/2013 |