7/5/16 - Final Decision signed. To stay involved and informed of implementation activities, see the SBEADMR IMPLEMENTATION WEBSITE (currently under construction): www.fs.usda.gov/goto/SBEADMRimplementation
Location
A maximum of 120,000 acres of commercial and noncommercial treatments are proposed within defined Priority Treatment Areas(PTAs); PTAs comprise a maximum of 207,600 acres in the Agency Preferred Alt.
Project timeline
1
NOI in Federal Register
07/31/2013
2
DEIS NOA in Federal Register
05/29/2015
3
FEIS NOA in Federal Register
02/05/2016
4
Objection Period Start
02/05/2016
5
Decision
07/2016 (Estimated)
6
Implementation
07/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other; Stewardship Contract, Consolidated Appropriations Resolution Of 2003 |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Special Products Sales; Timber Sales (Salvage); Timber Sales (Green) |
| Spruce Beetle Epidemic and Aspen Decline Management Response Final ROD | Decision Signed Date: 07/05/2016 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Grand Mesa Uncompahgre and Gunnison National Forest All Units |
| Legal Land Description | Not Applicable |