Expansion of existing USA #1-16SC well pad, drilling two new wells on the well pad, and construction/installation of approximately 1.37 miles of buried natural gas and water lines along the Buzzard Divide Road (NFSR 265). Ownership change 9/2016.
Location
Sections 16-18, T. 9 S., R. 92 W., and Section 12, T. 9 S., R. 93 W., 6th P.M.
Project timeline
1
Scoping Start
01/07/2015
2
Comment Period
09/2016 (Estimated)
3
Objection Period Start
04/2017 (Estimated)
4
Decision
05/2017 (Estimated)
5
Implementation
06/2017 (Estimated)
NEPA / regulatory detail
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Grand Valley Ranger District |
| Legal Land Description | Sections 16-18, T. 9 S., R. 92 W., and Section 12, T. 9 S., R. 93 W., 6th P.M. |