CBMR has formally requested site-specific review and analysis under NEPA procedures for elements of the Master Development Plan that was accepted by the Forest Service in 2013. See item 23 for more information.
Location
Crested Butte Mountain Resort
Project timeline
1
NOI in Federal Register
05/06/2015
2
DEIS NOA in Federal Register
02/09/2018
3
FEIS NOA in Federal Register
02/15/2019
4
Objection Period Start
02/15/2019
5
Decision
06/2019 (Estimated)
6
Implementation
06/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Land Use Adjustments; Special Use Authorizations; Plan Amendment |
| Crested Butte Mountain Resort (CBMR) - Proposed Teo Drainage & Summer Use Improvements | Decision Signed Date: 06/04/2019 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Gunnison Ranger District |
| Legal Land Description | T13S, R86W, Sec 29, 30, 31, 25, 36 |