Replace structurally deficient Willow Creek Bridge #1 on NFSR 765 approximately 1.85 miles east of NFSR 742 and Willow Creek Bridge #2 (approximately 3.25 miles east of FS Road 742)at the existing bridge locations and move utilities from bridges.
Location
Willow Creek near Taylor Reservoir and Taylor Park, Gunnison County, Colorado
Project timeline
1
Scoping Start
05/15/2015
2
Decision
06/2015 (Estimated)
3
Implementation
09/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Improvements/Construction; Watershed Improvements |
| Categorical Exclusion and Decision Memo | Decision Signed Date: 06/02/2015 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Gunnison Ranger District |
| Legal Land Description | T14S, R82W, Sections 22 and 25, 6th PM |