Re-route of the proposed Crane Lake trail alignment.
Location
Grand Mesa National Forest, Flowing Park trailhead below Flowing Park reservoir east to Crane Lake.
Project timeline
1
Scoping Start
02/28/2017
2
Decision
08/2017 (Estimated)
3
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Crane lake Trail Alignment and Construction | Decision Signed Date: 08/08/2017 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Grand Valley Ranger District |
| Legal Land Description | Pt #1- 38/58/51 N by 108/06/27 W Flowing Park Trailhead - 38/57/17 N by 108/06/15 W |