Mt Hatten Project is a radio repeater installation project, the system operates in the VHF band, power output is rated at 8 watts and is supplied by two solar panels and storage batteries. Ground disturbance will be the placement of 4 concrete pads.
Location
6th Principal Meridian, Colorado T.12S., R.92W., sec 4 NW1/4NW1/4 Chalk Mountain Quad, Grand Mesa National Forest
Project timeline
1
Scoping Start
06/15/2020
2
Decision
10/2021 (Estimated)
3
Implementation
10/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Grand Valley Ranger District |
| Legal Land Description | 6th Principal Meridian, Colorado T.12S., R.92W., sec 4 NW1/4NW1/4 Chalk Mountain Quad, Grand Mesa National Forest |