Installation of a portable Versa Tower repeater on top of S. Matchless Mountain to provide administrative radio coverage in the Taylor Park area. This is needed to address the safety concern of the area being a large dead zone for radio coverage.
Location
Three miles west of Taylor Park Reservoir Dam
Project timeline
1
Scoping Start
07/03/2017
2
Decision
07/2017 (Estimated)
3
Implementation
08/2017 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| South Matchless Repeater | Decision Signed Date: 07/21/2017 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Gunnison Ranger District |