Decision Memo Completed

South Matchless Repeater

Grand Mesa, Uncompahgre and Gunnison National Forests Gunnison, Colorado Gunnison Ranger District

Installation of a portable Versa Tower repeater on top of S. Matchless Mountain to provide administrative radio coverage in the Taylor Park area. This is needed to address the safety concern of the area being a large dead zone for radio coverage.

Location

Three miles west of Taylor Park Reservoir Dam

Project timeline

1
Scoping Start
07/03/2017
2
Decision
07/2017 (Estimated)
3
Implementation
08/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.12 (3), 36 Cfr 220.6(D)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
South Matchless RepeaterDecision Signed Date: 07/21/2017
ForestsGrand Mesa, Uncompahgre and Gunnison National Forests
DistrictsGunnison Ranger District
Legal Land DescriptionNot Applicable