Black Hills Energy purchased Source Gas. Re-issue permits to BHE for the Redvale to Olathe 10 inch gas line; Montrose Expansion Project Distribution Line.
Location
Redvale Olathe gas line crosses Uncompahgre Plateau. Lot 6 Microwave Tower at Raspberry Comm Site, Unc. Plateau; Montrose Expansion distribution line is north of Ouray.
Project timeline
1
Scoping Start
07/15/2018
2
Decision
02/2021 (Estimated)
3
Implementation
02/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Black Hills Energy Authorization Re-Issuances | Decision Signed Date: 02/22/2021 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Grand Mesa Uncompahgre and Gunnison National Forest All Units |
| Legal Land Description | Not Applicable |