Decision Memo Completed

Black Hills Energy Authorization Re-Issuances

Grand Mesa, Uncompahgre and Gunnison National Forests Montrose; Ouray, Colorado Grand Mesa Uncompahgre and Gunnison National Forest All Units

Black Hills Energy purchased Source Gas. Re-issue permits to BHE for the Redvale to Olathe 10 inch gas line; Montrose Expansion Project Distribution Line.

Location

Redvale Olathe gas line crosses Uncompahgre Plateau. Lot 6 Microwave Tower at Raspberry Comm Site, Unc. Plateau; Montrose Expansion distribution line is north of Ouray.

Project timeline

1
Scoping Start
07/15/2018
2
Decision
02/2021 (Estimated)
3
Implementation
02/2021 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Black Hills Energy Authorization Re-IssuancesDecision Signed Date: 02/22/2021
ForestsGrand Mesa, Uncompahgre and Gunnison National Forests
DistrictsGrand Mesa Uncompahgre and Gunnison National Forest All Units
Legal Land DescriptionNot Applicable
Special use management