Replace existing dilapidated/unsafe storage and office facilities with one building at existing administrative site in North Delta. Demolish other buildings at site.
Location
North Delta, Colorado (existing administrative site outside proclamation boundaries)
Project timeline
1
Scoping Start
06/18/2019
2
Decision
06/2019 (Estimated)
3
Implementation
06/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| North Delta Administrative Site Replacement Building | Decision Signed Date: 06/25/2019 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Grand Mesa Uncompahgre and Gunnison National Forest All Units |
| Legal Land Description | Not Applicable |