To replace a transformer with a reactor and realign varroa structures within the existing Sunshine Sub substation.
Location
N.M.P.M. T.42N.,R.9W., Section 19: NE1/4SW1/4
Project timeline
1
Scoping Start
04/01/2019
2
Decision
11/2019 (Estimated)
3
Implementation
11/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Norwood Ranger District |
| Legal Land Description | N.M.P.M.T.42N., R.9W.,Section 19: NE1/4SW1/4 |