Environmental Assessment Completed

San Miguel Power Association 44kV Red Mountain Transmission Line Rebuild

Grand Mesa, Uncompahgre and Gunnison National Forests Ouray; San Juan, Colorado Ouray Ranger District

SMPA has applied for a special use permit to rebuild, operate and maintain the ~16 mile transmission line along Hwy 550 between the Ouray North and the Burro Bridge Substations on the GMUG and San Juan National Forests.

Location

The proposed transmission line rebuild would occur over ~16.2 miles of NFS and private land along Hwy 550 between Ouray and Durango on the GMUG and San Juan National Forests.

Project timeline

1
Scoping Start
04/06/2020
2
Comment Period
04/06/2020
3
Objection Period Start
02/03/2021
4
Decision
05/2021 (Estimated)
5
Implementation
05/2021 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityElectric Transmission; Special Use Authorizations
Red Mountain Pass (Burro Bridge to Ouray North) 44kV Transmission Line Rebuild San Miguel Power AssociationDecision Signed Date: 05/25/2021
ForestsGrand Mesa, Uncompahgre and Gunnison National Forests
DistrictsOuray Ranger District
Legal Land DescriptionNot Applicable
Special use management