Decision Memo Completed

Tomahawk Reservoir Spillway Reconstruction Project

Grand Mesa, Uncompahgre and Gunnison National Forests Gunnison, Colorado Grand Mesa Uncompahgre and Gunnison National Forest All Units

Repair the spillway under direction of the Colorado Dam Inspector in order to pass State of Colorado Dam Safety Inspection and provide for resource protection while allowing the State-issued water rights holder to continue exercising their rights.

Location

T12S, R89W, Section 14, 6th Principal Meridian

Project timeline

1
Scoping Start
05/28/2020
2
Decision
10/2020 (Estimated)
3
Implementation
10/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Tomahawk Reservoir Spillway Reconstruction ProjectDecision Signed Date: 10/28/2020
ForestsGrand Mesa, Uncompahgre and Gunnison National Forests
DistrictsPaonia Ranger District
Legal Land DescriptionT12S, R89W, Section 14, 6th Principal Meridian
Special use management