Phase 2. Restore historic wetlands, reconnect the floodplain to the stream, build fish habitat, provide wildlife habitat, create fire brakes, and bolster drought resiliency. To achieve the objectives, we will continue building instream structures.
Location
Trail Creek, Gunnison Ranger District, near NRSR 748
Project timeline
1
Scoping Start
06/15/2022
2
Decision
08/2022 (Estimated)
3
Implementation
08/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| 2022-2023 Trail Creek Beaver Habitat Work | Decision Signed Date: 08/15/2022 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Gunnison Ranger District |
| Legal Land Description | T13S, R83W, Sections 13, 23 and 26 |