Environmental Assessment Completed

North Fork Mancos Master Development Plan Supplement

Grand Mesa, Uncompahgre and Gunnison National Forests Delta; Gunnison, Colorado Paonia Ranger District

Based on additional analysis of emissions and climate change effects, the BLM will decide whether to approve, approve with modifications, or disapprove APDs. The Forest Service will issue a separate decision regarding SUPOs on NFS lands.

Location

T10S, R90W, Sections 16-21, 28-33; T11S, R90W, Sections 3-10, 16-22, 27-31; T12S, R89W, 17-20; T12S, R90W, 3-11, 13-14, 18-19, 24, and 30; and T12S, R91W, Sections 11-14, 23-26

Project timeline

1
Scoping Start
05/10/2023
2
Comment Period
05/17/2023
3
Objection Period Start
11/29/2023
4
Decision
03/2024 (Estimated)
5
Implementation
06/2024 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityMinerals Or Geology Plans Of Operations
Surface Use Plan of Operations Approvals Associated with North Fork Mancos Master Development Plan for Oil and Gas Exploration and DevelopmentDecision Signed Date: 03/20/2024
ForestsGrand Mesa, Uncompahgre and Gunnison National Forests
DistrictsPaonia Ranger District
Legal Land DescriptionT10S, R90W, Sections 16-21, 28-33; T11S, R90W, Sections 3-10, 16-22, 27-31; T12S, R89W, 17-20; T12S, R90W, 3-11, 13-14, 18-19, 24, and 30; and T12S, R91W, Sections 11-14, 23-26
Minerals and geology