Forest Service proposes to authorize Rocky Mountain Natural Gas, LLC to install 9,355 linear feet of conductor wire with 4 test stations and 14 solid state decouplers on its existing natural gas pipeline on the Uncompahgre Plateau.
Location
Existing RMNG pipeline corridor on the Uncompahgre Plateau
Project timeline
1
Scoping Start
06/01/2023
2
Decision
09/2023 (Estimated)
3
Implementation
05/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Natural Gas |
| Rocky Mountain Natural Gas, LLC Cathodic Protection (Uncompahgre Plateau- OUR703 Amendment 1) | Decision Signed Date: 09/29/2023 |
| Forests | Grand Mesa, Uncompahgre and Gunnison National Forests |
| Districts | Norwood Ranger District; Ouray Ranger District |
| Legal Land Description | TBD |