Trench and bury approximately 0.6 miles of new water pipeline to provide water to an existing livestock water tank in the Athens allotment. The majority of the project will occur in the adjacent Bandito Allotment.
Location
Athens Allotment on the Carrizo Unit
Project timeline
1
Scoping Start
08/02/2012
2
Comment Period
08/02/2012
3
Decision
09/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Grazing Allotment Management; Rangeland Vegetation Improvements; Grazing Structural Improvements |
| Forests | Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands |
| Districts | Comanche Ranger District |
| Legal Land Description | SW 1/4 Sec 11, T33S, R47W |