IREA is proposing to rebuild approximately 14,431 linear feet of existing powerline that provides electric service to residents in the Spring Creek Ranch area. On private land an additional 7,811 feet would be rebuilt as part of the project.
Location
Spring Creek Ranch
Project timeline
1
Scoping Start
04/04/2014
2
Comment Period
04/17/2014
3
Decision
08/2014 (Estimated)
4
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| IREA Spring Creek Ranch Overhead Powerline Rebuild | Decision Signed Date: 08/11/2014 |
| Forests | Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands |
| Districts | South Platte Ranger District |
| Legal Land Description | T8S,R70W, Sec(s) 16,20,29,32 |