Colorado Central Telecom is proposing new construction to add a 40' tower and 6'x10' shed with .03 new disturbance. AT&T plans to replace their existing tower with a new tower. T-Mobile plans to add a new 6'x10' equipment shed.
Location
The existing Granite Communications Site.
Project timeline
1
Scoping Start
07/18/2017
2
Decision
11/2017 (Estimated)
3
Implementation
08/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Granite Communications Site. | Decision Signed Date: 11/02/2017 |
| Forests | Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands |
| Districts | Leadville Ranger District |
| Legal Land Description | Not Applicable |