IREA proposes to rebuild and upgrade an existing 44-kilovolt(kV) transmission line to 115 kV from the west side of Kenosha Pass near Jefferson, CO to the Roberts Tunnel Power Generation Station near Grant, CO.
Location
The rebuild area involves approximately 6.1 miles length of National Forest System lands in a 50' width right of way, associated temporary access routes, and 2.4 miles of other lands.
Project timeline
1
Scoping Start
11/15/2017
2
Comment Period
09/18/2018
3
Decision
11/2018 (Estimated)
4
Implementation
10/2019 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Electric Transmission; Special Use Authorizations |
| IREA Kenosha Pass to Roberts Tunnel Powerline Rebuild | Decision Signed Date: 11/14/2018 |
| Forests | Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands |
| Districts | South Platte Ranger District |
| Legal Land Description | Sections 7, 8 & 9 of Township 7S, Range 74W and Sections 11, 12, 14, 15, 22, 27, 28 & 33 of Township 7S, Range 75W, of the 6th Principal Meridian, Park County, Colorado. |