The Lake County BOCC have requested a special use permit from the FS to maintain and use their decreed water right, 98CW173, from the state of CO that occurs on NFS Lands. The proposal includes installation of a flume, headgate, and water pipeline.
Location
T.11S, R.81W, Sec. 12 NW 1/4 SE 1/4 6th P.M. Mt. Elbert USGS Quadrangle
Project timeline
1
Scoping Start
07/24/2019
2
Decision
03/2020 (Estimated)
3
Implementation
04/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lake County BOCC Water Transmission Pipeline SUA | Decision Signed Date: 03/10/2020 |
| Forests | Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands |
| Districts | Leadville Ranger District |
| Legal Land Description | Not Applicable |