USFS proposes to breach the southern dam using machinery or high power water to comply with a written order issued to the USFS from the CDWR. This may involve improvement to NFST 1455 including tree removal/limbing for access.
Location
Lower Harvard Lake, T. 13 S., R. 79 W., Sec. 29, 6th PM
Project timeline
1
Scoping Start
11/04/2019
2
Decision
01/2020 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands |
| Districts | Leadville Ranger District |
| Legal Land Description | Not Applicable |