There is a need to increase parking capacity at existing trailheads to provide for increasing visitor use and to provide opportunities for users with different space requirements. The project changed to three trailheads.
Location
T51N, R7E, Sec 14 - Brown%u2019s Creek TH T48N, R8E, Sec 7 - Shirley Site T15S, R80W, Sec 33 - Grizzly TH T13S, R79W, Sec 31 - N Cottonwood TH T14S, R80W, Sec 30 - Ptarmigan Lake TH
Project timeline
1
Scoping Start
06/21/2021
2
Decision
02/2024 (Estimated)
3
Implementation
07/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (22), 36 Cfr 220.6(E)(22) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Developed Site Management |
| FY21 Trailhead Expansions Ptarmagin, Grizzly and Brown's Creek | Decision Signed Date: 02/09/2024 |
| Forests | Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands |
| Districts | Salida Ranger District |
| Legal Land Description | Not Applicable |