Proposal to amend the existing permit issued to Xcel Energy to approve actions to rebuild the existing transmission line. The BLM is lead agency. https://eplanning.blm.gov
Location
South east of Poncha Springs, Colorado
Project timeline
1
Scoping Start
07/27/2022
2
Comment Period
08/08/2023
3
Decision
07/2024 (Estimated)
4
Implementation
09/2024 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Special Use Authorizations |
| XCEL ENERGY%u2019S CIRCUIT 9811 115KV TRANSMISSION LINE REBUILD | Decision Signed Date: 07/01/2024 |
| Forests | Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands |
| Districts | Salida Ranger District |
| Legal Land Description | Not Applicable |