This project originally planned to occur on National Forest lands is cancelled and a new project that includes transmission line rebuild proposals on both National Forest and BLM lands will be posted at a later date.
Location
Line 9255 is located along US Highway 24 from Otero Tap station to Twin Lakes to Malta Substation. Line 9254/9257 starts south of Leadville and runs north to the Climax Substation & Robinson on CO-91.
Project timeline
1
Scoping Start
10/14/2022
2
Comment Period
11/16/2022
3
Decision
11/2024 (Estimated)
4
Implementation
11/2024 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Forests | Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands |
| Districts | Leadville Ranger District |
| Legal Land Description | Not Applicable |