Conduct an EIS on Fruitland coal bed methane (CBM) development, north of Southern Ute line, including the HD mountains,by the USFS & BLM.
Location
HD Mountains, Southern Ute land, private land
Project timeline
1
NOI in Federal Register
04/04/2000
2
DEIS NOA in Federal Register
06/10/2004
3
FEIS NOA in Federal Register
08/10/2006
4
Decision
04/2007 (Estimated)
5
Implementation
07/2007 (Estimated)
NEPA / regulatory detail
| Special Authority | Forest Service Energy Implementation Plan |
| Notice and Comment Regulation | 215 |
| Project Activity | Harzardous Waste Compliance Actions |
| Northern San Juan Basin Coal Bed Methane Project | Decision Signed Date: 04/04/2007 Legal Notice Date: 04/05/2007 |
| Forests | San Juan National Forest |
| Districts | Columbine Ranger District |
| Legal Land Description | Not Applicable |