Construct in-stream rock structures and stabilize eroding stream banks on Hermosa Creek along a 1 mile reach adjacent to Forest Road 578.
Location
Along the main stem of Hermosa Creek upstream from the confluence with the East Fork and downstream from the confluence with Hotel Draw.
Project timeline
1
Scoping Start
05/12/2011
2
Decision
08/2011 (Estimated)
3
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Watershed Improvements |
| Hermosa Creek Fish Habitat Improvement Project | Decision Signed Date: 08/03/2011 |
| Forests | San Juan National Forest |
| Districts | Columbine Ranger District |
| Legal Land Description | T39N, R10W, sections 13, 14, and 24 |