Stream bank revegetation along approximately 100 feet of the Rito Blanco to treat impacts of dispersed camping
Location
East side of Pagosa Ranger District, on northwest bank of the Rito Blanco downstream of NFSR 024 road crossing.
Project timeline
1
Scoping Start
03/25/2014
2
Decision
09/2014 (Estimated)
3
Implementation
10/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (5), 36 Cfr 220.6(E)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Forests | San Juan National Forest |
| Districts | Pagosa Ranger District |
| Legal Land Description | T35N R1E Section 17 NMPM |