Installation of approximately 1000 feet of fiber optic cable within the existing access road at the Coal Bank Communications Site in order to connect both Tri-State and Verizon facilities to fiber optic internet capabilities.
Location
Coal Bank Pass Communications Site
Project timeline
1
Scoping Start
08/24/2016
2
Decision
08/2016 (Estimated)
3
Implementation
09/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| CenturyLink Fiber Optic Installation at Coal Bank Pass Communications Site | Decision Signed Date: 08/31/2016 |
| Forests | San Juan National Forest |
| Districts | Columbine Ranger District |
| Legal Land Description | T40N R8W section 32 |