Decision Memo Completed

Special Uses - LPEA at The Cliffs

San Juan National Forest La Plata, Colorado Columbine Ranger District

Issue Special Use Permit to La Plata Electric Association to install a buried powerline approximately 1400 feet long and 25 feet wide on Forest land, running from an existing communications site on Forest land to adjacent private land.

Location

Top of the Cliffs subdivision, south end of Missionary Ridge

Project timeline

1
Scoping Start
09/26/2016
2
Decision
12/2016 (Estimated)
3
Implementation
05/2017 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
LPEA, The Cliffs to Missionary Ridge Tie-InDecision Signed Date: 12/21/2016
ForestsSan Juan National Forest
DistrictsColumbine Ranger District
Legal Land DescriptionT36N R9W section 35