Authorize future construction and ground disturbing projects within the existing footprints and parameters as defined within the Comm Site Plan. Consists of four areas totaling about 4.75 acres.
Location
Missionary Ridge Communications Site, 5 miles NE of Durango, CO.
Project timeline
1
Scoping Start
03/02/2018
2
Decision
06/2018 (Estimated)
3
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Missionary Ridge Communications Site Potential Projects | Decision Signed Date: 06/27/2018 |
| Forests | San Juan National Forest |
| Districts | Columbine Ranger District |
| Legal Land Description | T36N R8W Section 30 |