Authorize the year-round use and maintenance of the existing Farrow & Peterson ditch and diversion structure, including relocation of the headgate and an in-river cross-vane structure. Total surface area on the Forest would be about 1/2 acre.
Location
Lower Piedra Road, about 1/2 mi north US160
Project timeline
1
Scoping Start
04/03/2018
2
Decision
07/2018 (Estimated)
3
Implementation
10/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Farrow & Peterson Ditch and Diversion - Use and Maintenance | Decision Signed Date: 07/16/2018 |
| Forests | San Juan National Forest |
| Districts | Columbine Ranger District |
| Legal Land Description | T34N R4W Section 8 |