Re-Authorization of approximately 4000 feet of buried pipeline (6 feet wide) within the H.E. Freeman Ditch, which transports water from Snow Creek to permittee's adjacent private land. No new disturbance.
Location
Just west of Hwy 160/Fosset Gulch Road intersection, paralleling the highway.
Project timeline
1
Scoping Start
06/29/2019
2
Decision
12/2019 (Estimated)
3
Implementation
12/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | San Juan National Forest |
| Districts | Columbine Ranger District |
| Legal Land Description | T 34N R 5W Sections 10 & 11 |