Environmental Assessment Completed

Minerals - Catamount Spring Creek Gas Wells and Pipeline

San Juan National Forest Archuleta; La Plata, Colorado Columbine Ranger District

Construction of an 8.4 mile pipeline system and the expansion of one existing gas well pad to facilitate re-completion of one existing gas well and horizontal drilling of seven new gas wells from the same pad.

Location

Spring Creek Road in the HD Mountains

Project timeline

1
Scoping Start
10/18/2022
2
Comment Period
12/15/2023
3
Objection Period Start
06/26/2024
4
Decision
08/2024 (Estimated)
5
Implementation
10/2024 (Estimated)

NEPA / regulatory detail

Special AuthorityForest Service Energy Implementation Plan
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations; Minerals Or Geology Plans Of Operations
Minerals - Catamount Spring Creek Gas Wells and PipelineDecision Signed Date: 08/20/2024
ForestsSan Juan National Forest
DistrictsColumbine Ranger District
Legal Land DescriptionT34N R6W
Minerals and geology