Decision Memo Completed

Special Uses - LPEA Bouse Underground Powerline Construction

San Juan National Forest La Plata, Colorado Columbine Ranger District

Permit installation of 335' of new underground powerline with above ground appurtenances along Bear Creek Road from an existing line to a private residence. Permit 20' wide, to occupy approximately 0.15 acres of FS land.

Location

Bear Creek Road north of Bayfield, CO

Project timeline

1
Scoping Start
06/14/2023
2
Decision
06/2023 (Estimated)
3
Implementation
07/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
LPEA Bouse Underground Powerline ConstructionDecision Signed Date: 06/26/2023
ForestsSan Juan National Forest
DistrictsColumbine Ranger District
Legal Land DescriptionT35N, R6W, Sec. 8, SE1/4