Six established and existing right of way permits have expired and need to be re-issued
Location
Various locations across the district
Project timeline
1
Scoping Start
01/12/2012
2
Decision
11/2018 (Estimated)
3
Implementation
11/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Reissue Six Small ROW Permits | Decision Signed Date: 11/16/2018 |
| Forests | Apache-Sitgreaves National Forests |
| Districts | Black Mesa Ranger District |
| Legal Land Description | T11N,R18E; T11N, R19E; T12N, R16E; T11N, R14E; T11N, R15E |