Replace a current cell tower due to failing structural components with a new functioning cell tower in the same location.
Location
Located at the Brookbank Communications Site near Forest Service Rd. 300 east of the Forest Lakes Community.
Project timeline
1
Scoping Start
04/08/2015
2
Decision
05/2015 (Estimated)
3
Implementation
06/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Brookbank Cellular One (Smith Bagley) Cell Tower Replacement | Decision Signed Date: 05/01/2015 |
| Forests | Apache-Sitgreaves National Forests |
| Districts | Black Mesa Ranger District |
| Legal Land Description | T11N R15E S21 |