Replacement of existing mobile trailer unit with a new trailer unit.
Location
Located at the Job Corp in Camp Shadow Pines.
Project timeline
1
Scoping Start
04/21/2015
2
Decision
12/2015 (Estimated)
3
Implementation
03/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Dept. of Public Safety Substation Office Replacement & Permit | Decision Signed Date: 12/10/2015 |
| Forests | Apache-Sitgreaves National Forests |
| Districts | Black Mesa Ranger District |
| Legal Land Description | T 12N, R 16E, Section 20 |