Decision Memo Completed

Navopache Electric Burton Road Powerline Maintenance & Rebuild

Apache-Sitgreaves National Forests Navajo, Arizona Lakeside Ranger District

Replace the existing power poles located on the 24.9kV distribution line along Burton Road.

Location

Section 24, T11N, R20E and Sections 17, 19, 20, 24, 29, 30 and 31 T11N R21E GSRM

Project timeline

1
Scoping Start
01/14/2016
2
Decision
04/2016 (Estimated)
3
Implementation
05/2016 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Navopache Electric Burton Road Powerline Maintenance & RebuildDecision Signed Date: 04/19/2016
ForestsApache-Sitgreaves National Forests
DistrictsLakeside Ranger District
Legal Land DescriptionSection 24, T11N R20E and Sections 17 19 20 24 29 30 and 31 T11N R21E GSRM
Special use management