Within the project area, the Lakeside Ranger District proposes to authorize the installation of new riser poles carrying upgraded circuits to provide power to several areas.
Location
The project area is located adjacent to the Camp Grace / Camp Tatiyee area, west of SR260 / White Mountain Boulevard and south of Wagon Wheel Road.
Project timeline
1
Scoping Start
04/22/2018
2
Decision
06/2018 (Estimated)
3
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission |
| NEC Line Reconstruction | Decision Signed Date: 06/01/2018 |
| Forests | Apache-Sitgreaves National Forests |
| Districts | Lakeside Ranger District |
| Legal Land Description | Township 9N, Range 22E, Gila & Salt River Meridian. |