Phase II will continue adding new fiber optic line on existing Navopache power lines between Eagar and Greer, AZ. Access for the project would be along existing forest and county roads and the power line right-of-way.
Location
The project will occur on the Springerville District of the Apache-Sitgreaves National Forests between Eagar and Greer, AZ.
Project timeline
1
Scoping Start
08/28/2019
2
Decision
12/2019 (Estimated)
3
Implementation
12/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Commnet Phase II, Fiber Optic Line Project | Decision Signed Date: 12/13/2019 |
| Forests | Apache-Sitgreaves National Forests |
| Districts | Springerville Ranger District |
| Legal Land Description | Not Applicable |