The project would amend an existing communication site lease to add an existing communication tower and allow for operation of the communication tower at an existing facility.
Location
Green's Peak Communication Site
Project timeline
1
Scoping Start
08/13/2020
2
Decision
05/2021 (Estimated)
3
Implementation
06/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| NPC Communication Site lease amendment | Decision Signed Date: 05/25/2021 |
| Forests | Apache-Sitgreaves National Forests |
| Districts | Springerville Ranger District |
| Legal Land Description | T8N R26E Sections 2 and 11, GSRM |