To permit the running of an underground line from the nearest transformer to private property in T10N, R20E, Section 3. The underground power line will cross less than 10 feet of National Forest System land.
Location
Navajo County, AZ
Project timeline
1
Scoping Start
09/28/2020
2
Decision
10/2020 (Estimated)
3
Implementation
10/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Navopache Underground Line Permit | Decision Signed Date: 10/13/2020 |
| Forests | Apache-Sitgreaves National Forests |
| Districts | Lakeside Ranger District |
| Legal Land Description | T10N, R20E, Section 3 |