Modify permit LAK401912 to authorize APS to modify its less than 33kV distribution powerline to construct a new 0.65-acre microgrid, backup power facility which would ensure electric service to Forest Lakes Community and Young during power outages.
Location
Off FS Rd 237, just off Hwy 260 between Heber & Forest Lakes
Project timeline
1
Scoping Start
01/01/2023
2
Decision
10/2023 (Estimated)
3
Implementation
10/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Electric Transmission; Special Use Authorizations |
| Arizona Public Services Powerline Permit Modification | Decision Signed Date: 10/25/2023 |
| Forests | Apache-Sitgreaves National Forests |
| Districts | Black Mesa Ranger District |
| Legal Land Description | GSRM Township 11N, Range 14E, Section 22, SE1/4 NW1/4 NW1/4 NE1/4 |