Decision Memo Completed

APS Microgrid Site

Apache-Sitgreaves National Forests Navajo, Arizona Black Mesa Ranger District

Modify permit LAK401912 to authorize APS to modify its less than 33kV distribution powerline to construct a new 0.65-acre microgrid, backup power facility which would ensure electric service to Forest Lakes Community and Young during power outages.

Location

Off FS Rd 237, just off Hwy 260 between Heber & Forest Lakes

Project timeline

1
Scoping Start
01/01/2023
2
Decision
10/2023 (Estimated)
3
Implementation
10/2023 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Special Use Authorizations
Arizona Public Services Powerline Permit ModificationDecision Signed Date: 10/25/2023
ForestsApache-Sitgreaves National Forests
DistrictsBlack Mesa Ranger District
Legal Land DescriptionGSRM Township 11N, Range 14E, Section 22, SE1/4 NW1/4 NW1/4 NE1/4
Special use management