Install fiber optic line along utility and road corridors within existing rights-of-way. Most cable will be installed above ground on existing utility poles. Directional boring will be used to place conduit where underground installation is needed.
Location
In various locations on the Lakeside and Springerville Districts in Navajo and Apache Counties
Project timeline
1
Scoping Start
04/23/2025
2
Decision
09/2026 (Estimated)
3
Implementation
10/2026 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Special Use Authorizations |
| Forests | Apache-Sitgreaves National Forests |
| Districts | Springerville Ranger District; Lakeside Ranger District |
| Legal Land Description | Not Applicable |