Buriial of a second 6" pipeline to be routed alongside the existing permitted pipeline and placement of an additional water storage facility, having a 350,000 gallon capacity.
Location
Along the western edge of the Village of Reserve, New Mexico.
Project timeline
1
Scoping Start
05/01/2013
2
Comment Period
05/01/2013
3
Decision
06/2013 (Estimated)
4
Implementation
07/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Village of Reserve Water System Upgrade | Decision Signed Date: 06/10/2013 Legal Notice Date: 06/19/2013 |
| Forests | Gila National Forest |
| Districts | Reserve Ranger District |
| Legal Land Description | E 1/2 NE 1/4, Section 11, T.7 S., R. 19 W., NMPM. |