Decision Memo Completed

Additional Use and Modification of the Existing Crown Castle Communication Facility on Jack's Peak

Gila National Forest Grant, New Mexico Gila National Forest All Units

Crown Castle GT Company, LLC is modifying its existing communication tower at the Jack's Peak Communication Site for greater stability. It is also going to allow T-Mobile and AB Spectrum to locate their antennas and repeater equipment on their site.

Location

Jack's Peak Communication Site, SE 1/4 NE 1/4 Section 7, T.20 S., R.15 W., NMPM.

Project timeline

1
Scoping Start
02/10/2014
2
Decision
03/2014 (Estimated)
3
Implementation
04/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Construction & Expansion of Crown Castle's Jack's Peak Comm SiteDecision Signed Date: 03/11/2014 Legal Notice Date: 03/11/2014
ForestsGila National Forest
DistrictsSilver City Ranger District
Legal Land DescriptionNot Applicable
Special use management