Crown Castle GT Company, LLC is modifying its existing communication tower at the Jack's Peak Communication Site for greater stability. It is also going to allow T-Mobile and AB Spectrum to locate their antennas and repeater equipment on their site.
Location
Jack's Peak Communication Site, SE 1/4 NE 1/4 Section 7, T.20 S., R.15 W., NMPM.
Project timeline
1
Scoping Start
02/10/2014
2
Decision
03/2014 (Estimated)
3
Implementation
04/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Construction & Expansion of Crown Castle's Jack's Peak Comm Site | Decision Signed Date: 03/11/2014 Legal Notice Date: 03/11/2014 |
| Forests | Gila National Forest |
| Districts | Silver City Ranger District |
| Legal Land Description | Not Applicable |