Environmental Assessment Completed

Arizona Interconnection Project (AIP) Access Roads Amendment

Gila National Forest Catron; Luna; Sierra; Socorro, New Mexico Gila National Forest All Units

El Paso Electric has applied to renew their permit on FS lands and amend right-of-way to include permanent access to existing authorized 345 kV transmission line for maintenance on BLM and FS lands. See http://www.blm.gov/nm/epeaccess for more info.

Location

Transmission line extends from Red Hill tie-in point in western New Mexico (north of Gila National Forest) to east of Luna Substation near Deming, New Mexico

Project timeline

1
Scoping Start
03/04/2014
2
Comment Period
07/27/2016
3
Objection Period Start
10/24/2016
4
Decision
07/2017 (Estimated)
5
Implementation
10/2017 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other; Nepa Document Prepared By Another Federal Agency
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations; Road Maintenance; Road Improvements/Construction
Arizona Interconnection Project (AIP) Access Roads AmendmentDecision Signed Date: 07/19/2017
ForestsGila National Forest
DistrictsBlack Range Ranger District; Quemado Ranger District; Silver City Ranger District
Legal Land DescriptionNot Applicable
Special use management