Allow Socorro Electric to add approx. 1 miles of standard above ground powerline on Forest Lands along County Road A010 to provide power to a private land inholding. Work would include removal of vegetation and digging holes for poles.
Location
Along Catron County road A010 right-of-way starting at the junction of Hwy 32
Project timeline
1
Scoping Start
01/23/2018
2
Decision
05/2018 (Estimated)
3
Implementation
12/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Socorro Electric Cooperative Electric Line Extension | Decision Signed Date: 05/01/2018 |
| Forests | Gila National Forest |
| Districts | Quemado Ranger District |
| Legal Land Description | T2S R17W SEC 15, 22 |