Purpose of project is to improve existing water sources on the Agua Fria Allotment. Improvements would benefit wildlife and livestock. Proposed to install approx. 2.7 miles of pipeline, 1 or 2 storage tanks, and 2 troughs.
Location
Located on the northern boundary of the district approximately 9 miles south of the community of Quemado and west of highway 32.
Project timeline
1
Scoping Start
12/12/2016
2
Decision
10/2020 (Estimated)
3
Implementation
03/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements; Grazing Structural Improvements |
| Forests | Gila National Forest |
| Districts | Quemado Ranger District |
| Legal Land Description | T1S R17W SEC 10,11,15 |